PROJECTS · FOLLOW-UP · 09/11/2026

Bioceanic Corridor: PY15 Lot 3 reaches 47.5% completion

MOPC · 6 November 2026: Lot 3, approximately 55 km between Mariscal Estigarribia and Pozo Hondo, is 47.5% physically complete. Heavy rain has required adjustments to ground preparation and compaction.

Radar Analysis: progress on one road lot does not mean the entire corridor is operational. ANDE is also running an estimated USD 31.13 million international tender for two substations; it has not yet been awarded.

READ UPDATE →
RADAR PROJECTS

The projects transforming Paraguay

A selective editorial observatory of the projects with the greatest potential to reshape Paraguay’s economy and territory. We track background, capital, stage, next milestones and business impact.

Explore the investment and incentives map ↗

Inventory baseline: September 2026 · Editorial follow-up: 13 November 2026. MOPC reports over 36% progress on Avelino Martínez and 64% on the San Lorenzo drainage project. These infrastructure developments are tracked separately, without automatically expanding the 21-project strategic inventory or combining budgets.
CAPITAL UNDER EXECUTIONData validation in progressOnly projects with verified evidence are included.
COMMITTED CAPITALData validation in progressFID, financing or closed contract
CAPITAL IN STRUCTURINGData validation in progressEngineering, financing or advanced tendering
PROJECTS MONITORED21Initial strategic selection 2026–2035
UPDATE · 14 NOVEMBER 2026 · Graneros del Sur: the MOPC reports ongoing rehabilitation of 23 km of Route D054 (Lot 2, La Paz–Capitán Miranda), within a 58.4 km corridor. These works are distinct from tender 488026 for feasibility studies and port-access planning. Read the follow-up and official source
INVESTMENT MAP

Where capital is moving

Click a map point or use the filters. Locations represent the project area and are not necessarily exact construction coordinates.

Base map: OpenStreetMap · Territorial reference locations.
MONITORING PRIORITY

What deserves attention now

This is not a ranking. It is an editorial selection of projects whose scale, stage or spillover potential justifies continuous monitoring.

PRIORITY A

Paracel

Concepción · Industry

USD 2.900 M
Monitoring: enabling infrastructure, industrial schedule and the forestry-logistics ecosystem.
PRIORITY A

ATOME Villeta

Villeta · Industry / Energy

USD 665 M
Monitoring: post-FID execution, EPC, schedule and development of the Villeta industrial hub.
PRIORITY A

Bioceanic Corridor

Chaco · Infrastructure / Logistics

Project system
Monitoring: bridge, linked roads, access works and effects on trade, logistics and territory.
RADAR INVENTORY

21 strategic projects under monitoring

The selection prioritizes scale, structural impact and the ability to monitor progress reliably. Other projects remain in the pipeline until validation is completed.

RADAR VIEW

Knowing how much a project costs is not enough

Radar Projects will track what changed, where capital is going, which milestones come next, which economic chains are forming and what business opportunities are emerging around each investment.

↑